Month 0
Purchase & demolition
The existing house comes down and the lot is cleared once the deal is firm.
Photographed on site
-
Month 1
Excavation & foundation
Dig, footings, walls poured, then services run to the building.
Photographed at 9-Plex Inglewood
-
Month 2
Framing
Main and upper floors stood and braced on the foundation.
Photographed at 8-Plex Prince Charles
-
Month 3
Roof & envelope
Trusses set, sheathing on, windows in, building wrapped.
Photographed at 8-Plex Allendale
-
Month 4
Exterior & rough-ins
Siding and trim outside; mechanical, electrical and insulation inside.
Photographed at 9-Plex Inglewood
-
Month 5
Drywall
Board, tape and paint, then interior doors hung.
Photographed at 8-Plex Glenwood
-
Month 6
Interior finishing
Kitchens, bath tile, flooring and fixtures land suite by suite.
Photographed at 8-Plex Sherwood Park
-
Month 7
Site works
Walkways formed and poured, parking and landscaping complete.
Photographed at 8-Plex Sherwood Park
-
Month 8
Pre-leasing & handover
Units advertised and leased ahead of closing, then keys.
Photographed at 7-Plex Crawford Plains
Months are counted from a firm deal and describe the typical sequence, not a schedule. Construction timelines move with weather, trades, inspections, supply and municipal approvals, and an individual project can run materially longer or shorter than the eight months shown. Nothing here is a commitment to a completion date.